Earthwork Excavation Calculator
Estimate the cost of a rectangular excavation from its length, width, depth and a price per cubic metre, plus the loose (swelled) volume and the number of truck loads to haul it away. Use it to budget foundation, basement or trench digs.
Last updated: September 2026
Total Excavation Cost
$15,000.00
Formula below · 2 sources (osha.gov, cat.com) · Updated Sep 2026
Compare with similar
About this calculator
Excavation volume in place (the "bank" volume) is V = L × W × D for a rectangular dig, in cubic metres. The cost is V × the price per cubic metre, so enter a price quoted per bank cubic metre.
Dug soil takes up more room than it did in the ground because air gets between the pieces; this is called swell. Loose volume = bank volume × (1 + swell %). Typical swell is roughly 10–15% for sand and gravel, 20–40% for clay and common earth, and 50% or more for blasted rock; Caterpillar's earthwork reference tables give load factors for many materials. Truck loads = loose volume ÷ truck capacity, rounded up, since a part load is still a trip. Check the truck's weight limit as well as its volume: wet clay and rock can reach the legal weight before the body is full.
The calculator assumes vertical sides. Sloped or benched sides, which safety rules require for most excavations deeper than about 1.5 m (5 ft) unless shoring is used, add volume; compute those as separate shapes and add them.
How to use
Example (the defaults): 20 m × 10 m × 3 m at $25 per m³, 25% swell, 10 m³ trucks. Bank volume = 600 m³; cost = 600 × 25 = $15,000. Loose volume = 600 × 1.25 = 750 m³; truck loads = 750 ÷ 10 = 75. A 15 × 8 × 2.5 m foundation in sandy soil (15% swell): 300 m³, $7,500 at $25/m³, 345 m³ loose, 35 loads (34.5 rounded up).
Frequently asked questions
What is soil swell factor and why does it matter for excavation cost estimates?
Soil swell factor accounts for the increase in volume that occurs when soil is excavated from its natural, compacted state. A cubic metre of in-situ material becomes more than a cubic metre of loose, disturbed soil because air voids open up during digging. Sand and gravel swell by roughly 10–15%, clay and common earth by 20–40%, and blasted rock by 50% or more. If you ignore swell, you will underestimate the number of truck loads required to haul material away, leading to cost overruns and scheduling delays. Always multiply the in-situ volume by the appropriate swell factor when calculating haulage quantities.
How do I calculate the number of truck loads needed for an excavation project?
First calculate the in-situ excavation volume (L × W × D). Then apply the soil swell factor to get the loose (bulked) volume — for example, multiply by 1.20 for clay. Divide this bulked volume by the capacity of the dump trucks you are using; a standard 10-wheel truck typically carries 10–12 m³ per load. Round up to the nearest whole number since you cannot use a fraction of a truck trip. Also consider the truck cycle time, travel distance to the dump site, and any permit restrictions on truck gross weight that may reduce load capacity.
What factors affect the cost per cubic metre of excavation?
Excavation cost varies widely depending on soil type and hardness, equipment type (backhoe, bulldozer, or blasting for rock), site accessibility, excavation depth (deeper excavations require shoring and are slower), disposal distance, and local labour and fuel rates. Soft soils in accessible sites can cost as little as $10–20/m³, while hard rock removal requiring blasting or specialist equipment can exceed $100–200/m³. Seasonal conditions, mobilisation costs, and the volume of work also affect unit rates — larger projects typically command lower per-cubic-metre prices due to equipment utilisation efficiencies.
Related calculators
Sources & references
Think a result is wrong? Report a problem with this calculator.