Budget Variance Calculator (Percent Over or Under)
Compare actual spending with the planned budget and get the variance as a percentage of plan (and in dollars): positive is over budget, negative under.
Last updated: September 2026
Budget Variance
-10 %
Formula below · 2 sources (gao.gov, investopedia.com) · Updated Sep 2026
Compare with similar
About this calculator
Budget variance compares what you spent with what you planned:
variance (%) = (actual − planned) ÷ planned × 100
A positive result means you are over budget, a negative one under. With the defaults, a $50,000 budget and $45,000 spent: (45,000 − 50,000) ÷ 50,000 × 100 = −10%, $5,000 under plan. The tiles show the dollar variance and the share of the budget used.
This page gives the percentage; for the plain dollar difference by line item, the Budget Variance Analysis Calculator in the accounting section does that.
Reading the number
Many organisations set a control threshold, often around ±5–10%, beyond which a variance must be explained or corrected. Underspending is not automatically good: it can mean work is behind schedule.
Variance against the total budget only works at the end of a period or project. Partway through, compare spending with the budget for the work actually done. That is what earned value management does: cost variance CV = earned value − actual cost and the cost performance index CPI = EV ÷ AC. A project 40% complete that has spent 50% of its budget is overrunning even though it is still "under budget" in total.
How to use
Enter the planned budget for the period or project and the actual amount spent over the same period. Example 1 (the defaults): planned $50,000, spent $45,000: −10%, $5,000 under. Example 2: planned $150,000, spent $162,000: (162,000 − 150,000) ÷ 150,000 × 100 = +8%, $12,000 over. Example 3: a monthly marketing budget of $8,000 with $9,200 spent: +15%, $1,200 over, past a ±10% control threshold.
Frequently asked questions
How do you calculate budget variance?
Subtract the planned budget from actual spending, divide by the planned budget and multiply by 100. Planned $20,000, actual $23,000: 3,000 ÷ 20,000 × 100 = 15% over budget.
Is a negative budget variance good?
In this formula a negative variance means spending is below plan. That can be genuine savings, or a sign that work, purchases or hires are running late. Check progress before treating it as savings.
What variance is acceptable?
There is no universal rule. Many teams use ±5% or ±10% as a threshold that triggers an explanation, with tighter limits on large or fixed-price budgets.
How is this different from earned value cost variance?
Budget variance compares spending with the budget. Earned value cost variance (EV − AC) compares spending with the budgeted value of the work completed, so it shows overruns while a project is still in progress.
Related calculators
Sources & references
Think a result is wrong? Report a problem with this calculator.