Earned Value Management Calculator
Forecasts a project's final cost (Estimate at Completion) from BAC, actual cost, earned value and planned value by the CPI, CPI × SPI or budgeted-rate method.
Last updated: October 2026
Estimate at Completion (EAC)
$112,500.00
Formula below · 3 sources (ntrs.nasa.gov, energy.gov, projectmanager.com) · Updated Oct 2026
Compare with similar
About this calculator
Earned value management compares three numbers at a status date: planned value (PV, the budgeted cost of the work scheduled so far), earned value (EV, the budgeted cost of the work actually done) and actual cost (AC, what that work cost). Budget at completion (BAC) is the total budget.
The two indices
Cost performance index CPI = EV ÷ AC. Schedule performance index SPI = EV ÷ PV. Values below 1 mean over budget or behind schedule.
The forecast
The Estimate at Completion (EAC) is actual cost plus a forecast of the remaining work (BAC − EV). The three standard methods differ in how fast that remaining work is assumed to burn money:
CPI method: EAC = AC + (BAC − EV) ÷ CPI, which equals BAC ÷ CPI. CPI × SPI method: EAC = AC + (BAC − EV) ÷ (CPI × SPI), for when schedule pressure is expected to drive cost too. Budgeted rate: EAC = AC + (BAC − EV), for when the overrun was a one-off.
The CPI method is the most common default once a project is about 20% complete and its CPI has settled.
How to use
Enter BAC, AC, EV and PV in the same currency and pick a method. Defaults: BAC $100,000, AC $45,000, EV $40,000, PV $50,000. CPI = 40,000 ÷ 45,000 = 0.889 and SPI = 40,000 ÷ 50,000 = 0.80. CPI method: 45,000 + 60,000 ÷ 0.889 = $112,500, a $12,500 overrun. CPI × SPI method: 45,000 + 60,000 ÷ (0.889 × 0.80) = $129,375. Budgeted rate: 45,000 + 60,000 = $105,000. A project running under budget: BAC $250,000, AC $80,000, EV $90,000 gives CPI 1.125 and an EAC of $222,222.22 by the CPI method.
Frequently asked questions
What is the difference between CPI and SPI?
CPI = EV ÷ AC measures cost efficiency: 0.9 means $0.90 of planned work done for each $1 spent. SPI = EV ÷ PV measures schedule efficiency: 0.9 means 90% of the work planned by now is done. Below 1 is worse than plan for both.
Which EAC method should I use?
Use the CPI method when past cost efficiency is likely to continue, which is the usual assumption. Use CPI × SPI when you are behind schedule and expect catching up to cost extra. Use the budgeted rate only when the cause of the overrun has been removed.
What is ETC?
Estimate to Complete, the money still needed: ETC = EAC − AC. With the defaults and the CPI method, ETC = 112,500 − 45,000 = $67,500.
Why does the forecast change so much between methods?
Each method makes a different assumption about the remaining 60% of the work. When CPI and SPI are both well below 1, the CPI × SPI method divides by a small number and gives the most pessimistic forecast.
Related calculators
Sources & references
Think a result is wrong? Report a problem with this calculator.